-1
$\begingroup$

A can do as much work as C in 2 days and C does in 3 days as Much work as B in 4 days.what time B would require to do a work which A can finish in 16 Weeks?

I have tried:

I have calculated the Efficiency A:C as 1:2

and B:C as 3:4

Then I have calculated the overall efficiency as 4:6:8

A as 16 weeks B as When?

For that

16*6/4

I got 24 , but it wrong

What I am doing Mistake Please anyone Guide me for the Answer

1 Answers 1

0

Your mistake.

B's 4 day work = $\frac 4B$

C's 3 day work = $\frac 3C$

And these are equal so,

$\frac 4B = \frac 3C$

$\frac BC = \frac 43$

  • 0
    ok I have Understand, then what is the answer2017-02-10
  • 0
    You are helping a lot, I have found out answer, can you put your own answer,I can check with you , you are helping me a lot2017-02-10
  • 0
    Yes the Answer is 128/3 ,My Answer2017-02-10
  • 0
    Yes your answer is correct. And I am fond of aptitude. So mine pleasure to help you.2017-02-10
  • 0
    Any doubt you have?2017-02-10